Progress on Water and Sewerage Infrastructure in Sozopol
Construction and installation activities for the reconstruction of the water and sewerage network in Sozopol are showing significant progress. Experts from "Water Supply and Sewerage - Burgas" EAD confirmed that the pressure pipe from the "Budzhaka 2" pumping station, spanning nearly a kilometer, is fully completed.
The project is part of the "Integrated Water Project for Burgas Region" – one of the largest investments in the water and sewerage sector in Bulgaria, financed under the "Environment" Program 2021-2027.
Main project parameters:
- Construction of over 10 kilometers of water supply and sewerage network.
- Construction of three sewage pumping stations.
- Total value of the engineering contract: nearly 5 million euros.
You may also like
Attention: Repairs on A1 "Hemus" near Varna! Traffic changes from April 29
Attention drivers: Roadworks continue on Krayezerna Street in Burgas
Updated Safety Base: New Opportunities at the "Varli bryag" Training Center
Burgas Celebrates 75 Years of Landscape Architecture with a Scientific Conference and Exhibition
Currently, a total of 11 out of 31 sites within the large-scale regional investment of over 210 million euros have already been put into operation. Work in Sozopol started in February and is being monitored by the local municipal authorities.