Dyulinski Pass: Clear deadlines for repairs
Full funding has been secured for the repair of the Dyulinski Pass in the Panitsovo – Gyulovtsa section. According to information from the Regional Administration in Burgas, asphalt laying will begin no later than August 15, and the deadline for completion of the project is November 15, provided there are no unforeseen circumstances.
"The company is fulfilling its commitments in accordance with the regulatory framework," stated Regional Governor Diko Dikov after an inspection of road sections in the region.
Infrastructure plans for the region
- Gyulovtsa – Orizare: After the completion of the Dyulinski Pass, the machinery will be directed here. The construction of new curbs and sidewalks is planned.
- Gyulovtsa – Sarafovo: Documentation is expected by the end of July, and construction could begin on September 1. The project includes a complete reconstruction with three layers of asphalt.
- Road III-99 (Otmanli – Yasna Polyana): An on-site inspection has been carried out, which confirmed that the contractor is working according to the requirements and the site is secured.
The repair activities are the result of a coordination meeting initiated by Deputy Regional Governor Veselin Anestiev, with the aim of strictly adhering to the deadlines for the three priority road sections.