Billions for "Hemus" without designs: Ivan Shishkov exposes the advance payment scheme

21.07.2026 | News

Minister Ivan Shishkov revealed how advance payments of billions of leva were distributed for road construction without finalized projects. See the details regarding the abuses involving "Avtomagistrali".

Снимка от Ewa Dryjanska, Wikimedia Commons (CC BY 3.0)

Billions for "Hemus" without designs: Ivan Shishkov reveals the scheme

The state has been distributing advances for road construction without having the necessary designs in place. This was stated by the Minister of Regional Development and Public Works, Ivan Shishkov, on bTV.

"This was a period of tightening the noose around the state's neck," the minister commented regarding the 2019-2020 period.

How the scheme works?

The problems with the "Hemus" motorway lots

Shishkov emphasized that for lots 7, 8, and 9, not only are the designs missing, but the route itself needs to be changed. Although the companies have received advance payments, construction is practically not taking place, and the prices of materials have skyrocketed.

Currently, the Ministry is conducting negotiations with the contractors to try to save the depreciation of the already paid funds and force the companies to start actual work on the sites.