Nesebar ends contract to demolish Amore restaurant in Elenite

26.11.2026

Nesebar council and Valdaram Building have agreed to cancel the contract. A new tender will be held, but no date has been set for the demolition.

Колаж: Снимка от Sóc Năng Động, Pexels (лиценз Pexels) • Снимка от Pixabay, Pexels (лиценз Pexels)

Nesebar council and the firm Valdaram Building have ended, by mutual consent, their contract to demolish the illegal two-storey Amore restaurant in the Talyana Beach complex at the Elenite resort. The contract, No. 233, was signed on 24 March 2026. This is clear from a council decision on a public information request, which secretary Dochka Marinova signed on 4 November 2026.

The council had agreed to pay the firm €35,000 plus VAT for the demolition. It now says a new tender under the Public Procurement Act will cover the demolition and the work that follows. It gave no deadline for the demolition.

On 10 July the council asked the contractor for the papers and documents on the work, which both the Spatial Planning Act and the contract itself require. Valdaram Building proposed on 20 July that the contract be ended by mutual consent. The termination agreement was signed on 28 October. The council did not say why the firm wanted to end the contract, or give any other reason for the termination.

Under the contract, the contractor had to draw up a health and safety plan and a construction waste management plan. No such plans have yet been agreed for the demolition. In February 2026 Taliyana Residence JSC filed plans for approval, but they were rejected because they did not meet Ordinance No. 2 of 22 March 2004 on minimum health and safety requirements for construction and assembly work.

Disciplinary proceedings under the Labour Code were held over the case. A chief expert in the "Construction Control" department was punished for failing to carry out official duties when checking the site. The head of the department received written instructions to improve how the department is organised and works.

The council says that as of June 2026 it had received 3 reports, 4 complaints and 2 objections about the building. The "Construction Control" department made 11 checks. On 6 of them, the inspectors were not given access to the site.

The order to remove the building, No. 1472 of 7 August 2019, stayed in force after court cases and appeals. The deadline for voluntary compliance ran out on 30 October 2025. The council then asked for €40,903 (80,000 leva) plus VAT from the 2026 budget for the forced demolition and the plans, and held a public tender for the demolition.